Dramatic Results
The results were dramatic, resulting in a bottom-line turnaround of the facility from losing $1 million per month to earning $150,000 per month over a six-month period.
Equally important, the primary quality problems were solved and other related output metrics also showed remarkable improvement:
- Quality improved from 1300 PPM (problems or defects per million part produced) to less than 50 PPM.
- On-time delivery improved from less than 50% to 100%.
- Program management results improved as new program launch results increased from 50% on-time to 100% on-time and on budget.
- Quotation response for new contracts improve from a 60-day to 24-day cycle time
- Lead time was reduced by over 50%.
- Monthly cash flow improved by more than 200%.